Installation of 132KV OHTL Towers

Project Info

Construction Date

03/05/17 - 09/08/17

Category

Completed Projects

Client Name

CPECC

Project Location

NORTH RUMAILA / BASRA

Current Progress

COMPLETED 100%

Project Information

Installation of 132 kv OHTL towers.

MFCO awaded a contract to supply and install 24 OHTL Towers to Rumaila Power Plant, in North Rumaila/ Basra.

This project included Procurement and installation of 24 Towers including the Concrete base for more 190m3.

Procurement including installation and lining the OHTL.

 